North Yorkshire Council revealed it is being forced to spend a further £300,000 on consultants designing the Harrogate Station Gateway — taking the total consultants’ bill to £2.3m.
Last year, the scheme had to be drastically altered following a legal challenge from Hornbeam Park Developments, a property company owned by businessman Chris Bentley.
The council admitted it had made a technical error during the consultation stages.
This meant it had to go back to the drawing board to ensure the legal threat subsided and the project could move forward, albeit on a much smaller scale.
The proposals now only include a redeveloped One Arch and Station Square, better traffic signals, a bus lane, a southbound cycle lane on Station Parade, new paving for pedestrians and cycling parking at Harrogate Station.
But those hoping to see a more ambitious scheme for pedestrians and cyclists have been disappointed after plans to part-pedestrianise James Street and reduce Station Parade to one lane were abandoned.
The project’s overall cost has spiralled since it was first announced in 2021 for £7.9m.
Even after several of its key elements have been removed, it will cost £12.1m with the bulk of the money coming from the government’s Transforming Cities Fund.
This week, the Conservative-run executive in Northallerton agreed to allocate £10m from its reserves that could be spent on potential overruns in ‘high-risk’ schemes, which includes the Harrogate Station Gateway.
The project was discussed again this morning during a meeting of local councillors. Coun Matt Walker (Liberal Democrat, Knaresborough West) asked council officer Matt Roberts if the authority anticipates any more money being spent on consultants.
The Local Democracy Reporting Service reported last year it had already handed £2m to consultancy firm WSP for design work.
Mr Roberts said an additional £300,000 would be spent on consultants which will take the project through to its construction stage.
He added:
“We don’t anticipate any further bills on consultants.”
He also gave timescales on when the project could finally see the light of day.
Mr Roberts said proposals to refurbish One Arch near Harrogate Bus Station will move forward before the rest of the scheme.
Traffic regulation orders for Station Parade that will see three disabled parking bays relocated are expected to go out for consultation next month.
Mr Roberts said “all being well” builders could start work in early 2025.
Following his presentation, Coun Chris Aldred (Liberal Democrat, High Harrogate and Kingsley) called on the council to publish its new designs for the scheme, which have not yet been released to the public.
He said this has created a “lot of murmuring and people not knowing what’s happening”.

Annual Tour de Aky set to hit £10,000 target
Harrogate bus staff nominated for national award
Parking warning issued after Burnsall car park closes
Spire Harrogate Clinic earns top housekeeping award
Otley music studio launches six-week daytime courses
New guide helps families find free and low-cost summer fun
Much-loved Slingsby Gin becomes new Festivals' partner
Princess Royal to become Great Yorkshire Show President
Concern over lack of consultation ahead of Lifeline cuts decision
Animal charity launches £2 million redevelopment appeal
Sneak peek: New Otley play area starts to take shape
Historic Harrogate pub named among the UK's best by The Telegraph
Police appeal to find wanted Harrogate man
Harrogate MP calls on new Prime Minister to overhaul 'broken' water industry
Harrogate nursery children get messy for International Mud Day
Harrogate Autumn Flower Show to celebrate 50th anniversary
Ripon swimming sensation secures dream move to US university
First look at Ripon Workhouse Museum after £2.8million refurb
"Serious unresolved legal questions" remain over A1(M) services plan, claim campaigners
North Yorkshire councillors with low attendance will not be asked to pay back allowances